19/1-2005 Kit arrival.
20-21/1 Everything is made account for.
EMP
22/1 Vertical stabiliser is started.
24/1 V.Stab ready for priming.
25/1 Rudder is started.
27/1 Rudder ready for priming
27/1 Horizontal stabiliser Started.
31/1 Horizontal stabiliser ready for priming.
1/2 Elevator started
8/2 Elevator ready for.
2/2 Tailcone started.
16/2 Tailcone ready for priming.
18/2 Tailcone/ Rudder / Vertical stab / horizontal stab / Elevator hasd now been primed
and it's time to rivet.
18/2 Vertical stabilizer done.
19/2 Rudder is done.
26/2 Tailcone rivetet.
27/2 Horizontal stablizer is done.
1/3 Elevator is done.
2/3 Attachment of controlsurfaces and stabilisers on the tailcone started.
6/3 The tailcone is completely assembled.
Fuselage
8/3 The cabin is started.
18/3 The bottom of the kabin/fuselage is done.
20/3 Firewall done.
20/3 The interior bodywork of the cabin is started.
2/4 The floor of the cabin is done.
14/4 The sides are done
18/4 The tailcone has been connected to the fuselage.
24/4 The bottom of the backseats is done.
25/4 The baggagecompartment is done (Floor and backwall).
26/4 The upper foreward fuselage assembly is done. (Where the instruments are mounted / dashboard).
2/5 The bagagedoor is done. (not mounted).
7/5 The brakesystem is done.
9/5 The Flapssystem is done.
13/5 All coverpanels is done.
14/5 Bagagedoor is mounted.
17/5 The controls are done.
18/5 Fitting of the cabintop is started.
21/5 The cabintop is fitted and mounted.
20/8 The backseats are done.
Wings
1/6 Construction of the wings is started.
2/6 The wingbars are done.
15/6 The wingribs are done.
16/6 The rear spar has been put on.
27/6 The outboard leading edges are done.
28/6 The topskin and the leading edges are rivet on the wings.
29/6 The fueltanks er started.
4/7 The left fueltank is done.
7/7 The right fueltank is done.
7/7 The ailerons are started.
11/7 Left aileron is done.
12/7 Right aileron is done.
11/7 The flaps are started.
15/7 Left flap done.
19/7 Right flap done.
27/7 Stallwarning is done.
5/8 Aileron actuation is done.
13/8 The bottomskins are done.
15/8 Wingtips are being fitted.
16/8 Light´s are fittet to the tips.
31/8 Wingtips are done.
Finishing
15/7 Starting the undercarriage and enginemount.
19/7 The undercarriage and the enginemount is mounted.
20/7 Step installation completed.
20/7 The door shells are epoxyed togeter.
3/8 Doorhinges on the right side is done.
21/8 Doorhinges on the left side is done.
6/9 The doorhandles are done.
23/10 Starting on the wheel fairings.
|